ADVAITAdvait Energy Transitions Ltd.

    Advait Energy Transitions gets ₹62 crore DGVCL order for underground cable

    • Order win
    • Power distribution infrastructure
    Steel high-voltage transmission towers and overhead power lines against a pale evening sky, with buildings in the distance
    Novoklimov, via Wikimedia Commons (CC0). Illustrative image.

    Advait Energy Transitions (NSE: ADVAIT) has received an order worth ₹62.05 crore including taxes from Dakshin Gujarat Vij Company Ltd (DGVCL), it said in a filing on 4 Nov 2026. The turnkey contract covers converting the existing 11/22 kV HT overhead network to underground cable in the Vyara Division.

    Key highlights

    • Order value: ₹62.05 crore including taxes
    • Order received on 3 Nov 2026
    • Execution period: 24 months after a 45-day commencement period
    • Awarded by DGVCL, a domestic entity

    The contract in numbers

    ItemDetail
    Awarded byDakshin Gujarat Vij Company Ltd (DGVCL)
    TypeTurnkey contract, domestic
    LocationVyara Division
    Value₹62.05 crore including taxes
    Order received3 Nov 2026
    Execution period24 months, excluding the monsoon period (June-July-August), after a 45-day commencement period
    ScopeSite survey, design, engineering, procurement, supply, transport, installation, testing, commissioning and documentation

    Scope of the Vyara Division work

    The company describes the order as a turnkey contract for converting the existing 11/22 kV HT overhead network to an underground cable system at Vyara Division under DGVCL. The scope includes site survey with underground utility verification using GPR and EPL, followed by design, engineering, procurement, supply, transport, installation, testing, commissioning and documentation.

    The work also includes SCADA compatible RMUs, removal of the DO overhead system, a higher-capacity transformer, SCADA compatible compact substations and conversion of the overhead LT network to underground using FSP/MSP. GIS mapping, referred to as Geo Urja Mapping and developed by GUVNL, and asset tagging are part of the job under the SI scheme.

    Timeline set out in the filing

    The order is to be executed within 24 months after a commencement period of 45 days. The monsoon period from June to August is excluded from the 24 months.

    The company says it received the order in the normal course of business.

    What the order means for Advait Energy Transitions' shareholders

    The order is worth ₹62.05 crore including taxes. The filing does not say how much of it will be recognised as revenue in each year, what margin the work carries, or how it compares with the company's existing orders.

    The next dated step in the filing is the 45-day commencement period, after which the 24-month execution period begins.

    Filed with NSE on . Reference: Original filing (PDF)

    Disclaimer:

    The information available on this article is provided for education and informational purposes only. It does not constitute or provide financial, investment or trading advice and should not be construed as an endorsement of any specific stock or financial strategy in any form or manner. We do not make any representations or warranties regarding the quality, reliability, or accuracy of the information provided. This website may contain links to third-party content. We are not responsible for the content or accuracy of these external sources and do not endorse or verify the information provided by third parties. We are not liable for any decisions made or actions taken based on the information provided on this website.