    Trident approves ₹4650 crore capacity expansion and modernisation

    • Guidance
    • Textile Products
    Spools of white thread
    Illustrative image. Photo: Janko Ferlič, via Wikimedia Commons (CC0)

    Trident (NSE: TRIDENT) said in a filing on 02 Nov 2026 that its Board approved a capacity expansion and modernisation project of ₹4650 crore across its business segments. The project covers yarn, sheeting, paper and a hybrid renewable energy plant.

    Key highlights

    • Total project size: ₹4650 crore
    • Budhni yarn investment: ₹1022 crore, completion by 31 Dec 2027
    • Dhar yarn facility investment: ₹1660 crore, completion by 30 Sep 2029
    • Existing Budhni utilisation: 94%

    The project in numbers

    ItemDetail
    Total project₹4650 crore approved on 02 Nov 2026
    Budhni yarn99,840 spindles added; 48,000 old spindles modernised to 70,176 new spindles; ₹1022 crore; by 31 Dec 2027
    Dhar yarn facility1,99,680 spindles; 179.2 acres leasehold land bought for about ₹106.09 crore; ₹1660 crore; by 30 Sep 2029
    Sheeting336 looms added; ₹1018 crore; by 31 Jan 2028
    PaperCapacity raised by 28 TPD; ₹296 crore; by 31 Mar 2028
    Hybrid power60 MW wind and 20 MW solar (AC); ₹654 crore; by 31 Oct 2028
    FinancingInternal accruals and debt

    Yarn accounts for most of the spend

    Yarn makes up the two largest components.

    The Dhar facility has the longest timeline, with completion on or before 30 Sep 2029. The Budhni work, which includes 2,400 new rotors replacing 960 old ones, is due by 31 Dec 2027. Budhni was running at 94% utilisation before the filing.

    Sheeting, paper and power

    The sheeting expansion of 336 looms is put at ₹1018 crore, paper at ₹296 crore and the hybrid power project at ₹654 crore. The company says the project is expected to strengthen its market position and improve energy efficiency.

    Paper was at 81% utilisation and sheeting at Sanghera, Punjab, at 58%, and the hybrid power capacity was at 100%, according to the filing. The filing does not say what revenue or profit the new capacity will add.

    What the project means for Trident's shareholders

    The project commits ₹4650 crore across several sites and timelines, with the company citing internal accruals and debt as the funding route. The company's market value at the 02 Nov 2026 close was ₹11,318 crore, and its latest quarter showed total income of ₹1,803.22 crore.

    The filing does not state the financing split between internal accruals and debt, the expected returns from the new capacity, or how the Dhar land cost fits within the Dhar investment figure. The next dated steps are the completion deadlines, starting with Budhni by 31 Dec 2027.

    Filed with NSE on . Reference: Original filing (PDF)

    Disclaimer:

    The information available on this article is provided for education and informational purposes only. It does not constitute or provide financial, investment or trading advice and should not be construed as an endorsement of any specific stock or financial strategy in any form or manner. We do not make any representations or warranties regarding the quality, reliability, or accuracy of the information provided. This website may contain links to third-party content. We are not responsible for the content or accuracy of these external sources and do not endorse or verify the information provided by third parties. We are not liable for any decisions made or actions taken based on the information provided on this website.