Steelcast approves ₹31 crore for 3250-ton foundry capacity addition
- Guidance
- Casting and foundry

Steelcast (NSE: STEELCAS) has approved a further investment of ₹31 crore in its Greenfield Foundry for a capacity addition of 3250 tons, it said in a filing on 13 Nov 2026. The addition is on top of 8500 tons approved on 29 Jul 2026, taking the total to 11750 tons.
Key highlights
- Additional investment: ₹31 crore in Greenfield Foundry
- Capacity addition: 3250 tons, by 31 Mar 2028
- Total approved: 11750 tons and ₹151 crore
- Existing installed capacity: 29000 tons at 60% utilisation
The capacity addition in numbers
| Item | Detail |
|---|---|
| Board approval | 13 Nov 2026 |
| Additional investment | ₹31 crore |
| Capacity to be added | 3250 tons |
| Deadline to add capacity | 31 Mar 2028 |
| Mode of financing | Internal accruals |
| Earlier approval | 8500 tons and ₹120 crore, approved 29 Jul 2026 |
| Combined total | 11750 tons and ₹151 crore |
| Existing installed capacity | 29000 tons, 60% utilisation based on the FY 2026-27 projection |
What the Board approved
Steelcast's Board approved on 13 Nov 2026 a further additional investment of ₹31 crore in Greenfield Foundry for a capacity addition of 3250 tons. The filing sets the period for adding the capacity at two years, by 31 Mar 2028.
The company says the capacity is needed to cater to increasing demand from customers. It says its present capacity utilisation is 60%, based on the projected utilisation for FY 2026-27, and that it expects to reach 90% by 31 Mar 2029. It says it now foresees more demand, which is why it added this step to the 8500 tons approved earlier.
How the step compares with existing capacity
The 3250 tons is 11.2% of the existing installed capacity of 29000 tons. Together with the earlier 8500 tons, the two additions equal 40.5% of that base, for a stated total of 11750 tons.
The ₹31 crore is 20.5% of the ₹151 crore combined investment, and about 0.8% of the company's market value of ₹3,897 crore at the 13 Nov 2026 close.
What the capacity addition means for Steelcast's shareholders
The step adds capacity at Greenfield Foundry and commits ₹31 crore of internal accruals to it, on top of ₹120 crore already approved. The filing does not say what revenue or profit the added capacity will bring, when within the two years the spending will fall, or whether customer demand for it has been contracted.
The next dated step in the filing is the deadline to add the capacity, 31 Mar 2028, and the company's stated target of 90% utilisation by 31 Mar 2029.
Filed with NSE on . Reference: Original filing (PDF)
Disclaimer:
The information available on this article is provided for education and informational purposes only. It does not constitute or provide financial, investment or trading advice and should not be construed as an endorsement of any specific stock or financial strategy in any form or manner. We do not make any representations or warranties regarding the quality, reliability, or accuracy of the information provided. This website may contain links to third-party content. We are not responsible for the content or accuracy of these external sources and do not endorse or verify the information provided by third parties. We are not liable for any decisions made or actions taken based on the information provided on this website.