    Acme Solar Holdings (NSE: ACMESOLAR) has commissioned a further 52.32 MW / 209.28 MWh battery energy storage component of its 300 MW / 1200 MWh FDRE project in Rajasthan, it said in a filing on 17 Nov 2026. The company's subsidiary, ACME Greentech Seventh Private Limited, has reached cumulative commissioned BESS capacity of 247.67 MW, and a power purchase agreement for the project is with SJVN Limited.

    The commissioning and what remains

    The additional BESS component was commissioned on 17 Nov 2026 at Village Kelan, Tehsil Chhatargarh, District Bikaner, Rajasthan, and its commercial operation date is 19 Nov 2026. The filing follows an intimation dated 27 Oct 2026 on the same project.

    With this step, ACME Greentech Seventh Private Limited has commissioned 247.67 MW / 990.68 MWh of discharge capacity, against a total installed BESS capacity of 247.67 MW / 1321 MWh. The filing gives the project's 300 MW / 1200 MWh discharge capacity as the full BESS scope. The power purchase agreement with SJVN Limited has been signed for this project.

    How it fits the company

    Acme Solar Holdings signed a power purchase agreement with NTPC for a 400 MW FDRE project on 28 Oct 2026, and the company's data show its latest quarter, Q2 FY27, with total income of ₹1,007.08 crore.

    What the BESS commissioning means for Acme Solar Holdings' shareholders

    The company is adding commissioned storage capacity at a Rajasthan project under a signed power purchase agreement. The filing does not state the cost of the BESS component, its financial impact, or the tariff and contracted capacity under the SJVN agreement, and it does not say when the remaining capacity will be commissioned.

    The next dated step is the commercial operation date of 19 Nov 2026.

    At a glance

    ItemDetail
    SubsidiaryACME Greentech Seventh Private Limited
    Project locationVillage Kelan, Tehsil Chhatargarh, District Bikaner, Rajasthan
    Commissioned on17 Nov 2026
    Commercial operation date19 Nov 2026
    Additional BESS component52.32 MW / 209.28 MWh
    Cumulative commissioned BESS247.67 MW / 990.68 MWh
    Power purchaserSJVN Limited (PPA signed)

    Filed with NSE on . Reference: Original filing (PDF)

    Disclaimer:

    The information available on this article is provided for education and informational purposes only. It does not constitute or provide financial, investment or trading advice and should not be construed as an endorsement of any specific stock or financial strategy in any form or manner. We do not make any representations or warranties regarding the quality, reliability, or accuracy of the information provided. This website may contain links to third-party content. We are not responsible for the content or accuracy of these external sources and do not endorse or verify the information provided by third parties. We are not liable for any decisions made or actions taken based on the information provided on this website.

    Get the Blacklitt app

    Hold Acme Solar Holdings Ltd.? See it with the rest of your portfolio

    Bring in your stocks and mutual funds once. Blacklitt sets them against a plan for your goals and risk, and tells you what to change and why.

    Fee-only SEBI Registered Investment Adviser, INA000022428. No commission from any fund house, broker or company.

    QR code: get the Blacklitt app on iPhone or Android

    Scan with your phone camera to get the app.

    Investment in securities market are subject to market risks. Read all the related documents carefully before investing.

    Related posts

    All Acme Solar Holdings Ltd. articles

    QR code: get the Blacklitt app on iPhone or Android
    Get the app
    Get the app