NHPCNHPC Ltd.

    NHPC settles Parbati-III claim with PLNT for ₹42.62 crore

    • Legal
    • Power
    A large blue hydroelectric turbine with a steel runner inside a concrete powerhouse, with access stairs and railings beside it.
    Florean Fortescue, via Wikimedia Commons (CC0). Illustrative image.

    NHPC (NSE: NHPC) has settled a claim by M/s Patel-L&T Consortium (PLNT) over delay in site handover and adverse geological conditions at the Parbati-III HE Project, it said in a filing on 19 Nov 2026. The final settlement amount is ₹42.62 crore, against the ₹256.10 crore PLNT had claimed.

    Key highlights

    • Final settlement amount: ₹42.62 crore
    • Amount claimed earlier by PLNT: ₹256.10 crore
    • Settlement amount released on 17 Nov 2026
    • Both parties withdrew their respective claims

    The settlement in numbers

    ItemDetail
    CounterpartyM/s Patel-L&T Consortium (PLNT)
    ProjectParbati-III HE Project
    MatterClaim on account of delay in handing-over of site and adverse geological conditions
    ForumConciliation Committee of Independent Experts (CCIE-III)
    Amount claimed by PLNT₹256.10 crore
    Final settlement amount₹42.62 crore
    Payment released17 Nov 2026
    ClaimsWithdrawn by PLNT and NHPC

    The settlement replaces a much larger claim

    The settlement sets the amount NHPC pays PLNT at ₹42.62 crore, against the ₹256.10 crore PLNT had claimed earlier. The settlement amount is about 16.6% of the claim, a gap of about ₹213.48 crore.

    The settlement was reached through the Conciliation Committee of Independent Experts, and NHPC has released the amount to PLNT on 17 Nov 2026.

    Background to the matter

    The filing refers to an earlier letter dated 14 Aug 2023 on the same matter. The filing does not describe that letter's contents beyond the reference.

    The claim relates to the Parbati-III HE Project, a hydroelectric project, and rests on two grounds named in the filing: delay in handing over the site and adverse geological conditions.

    What the settlement means for NHPC's shareholders

    The settlement fixes the amount NHPC pays on this claim at ₹42.62 crore and ends the claims between the two parties, as the filing describes it. The filing does not say what effect the settlement has on NHPC's financial results, or whether the amount was provided for earlier in its accounts.

    The filing does not give the reasoning for the gap between the claim and the settlement amount. No further dated step is stated in the filing.

    Filed with NSE on . Reference: Original filing (PDF)

    Disclaimer:

    The information available on this article is provided for education and informational purposes only. It does not constitute or provide financial, investment or trading advice and should not be construed as an endorsement of any specific stock or financial strategy in any form or manner. We do not make any representations or warranties regarding the quality, reliability, or accuracy of the information provided. This website may contain links to third-party content. We are not responsible for the content or accuracy of these external sources and do not endorse or verify the information provided by third parties. We are not liable for any decisions made or actions taken based on the information provided on this website.

    Get the Blacklitt app

    Hold NHPC Ltd.? See it with the rest of your portfolio

    Bring in your stocks and mutual funds once. Blacklitt sets them against a plan for your goals and risk, and tells you what to change and why.

    Fee-only SEBI Registered Investment Adviser, INA000022428. No commission from any fund house, broker or company.

    QR code: get the Blacklitt app on iPhone or Android

    Scan with your phone camera to get the app.

    Investment in securities market are subject to market risks. Read all the related documents carefully before investing.

    Related posts

    All NHPC Ltd. articles

    QR code: get the Blacklitt app on iPhone or Android
    Get the app
    Get the app