Diamond Power Infrastructure wins ₹708 crore HVDC conductor order
- Order win
- Power transmission equipment and cables

Diamond Power Infrastructure (NSE: DIACABS) has received a purchase order from Adani Energy Solutions Limited worth ₹707.80 crore including GST for AL-59 conductors for the ±800 kV HVDC Bhadla–Fatehpur project, it said in a filing on 19 Nov 2026. The company says the order marks its entry into HVDC transmission.
Key highlights
- Order value: ₹707.80 crore including GST at 18%
- Value excluding GST: ₹599.83 crore
- Quantity: 9,059.33 km of AL-59 conductors
- Deliveries to be completed by 31 Dec 2027
The order in numbers
| Item | Detail |
|---|---|
| Awarded by | Adani Energy Solutions Limited, a domestic entity |
| Purchase order | No. 4504006398 dated 19 Nov 2026, received 19 Nov 2026 |
| Value | ₹707.80 crore including GST at 18%; basic value ₹599.83 crore excluding GST |
| Quantity | 8,948.33 km AL-59 Lapwing and 111 km AL-59 Moose; total 9,059.33 km |
| Scope | Design, engineering, manufacture, testing, packing and supply on DAP basis |
| Delivery | Month-wise in line with the project schedule, complete by 31 Dec 2027 |
| Pricing | Commodity back-to-back; base LME aluminium USD 2,550 per MT, premium USD 106 per MT, USD/INR 87 |
| Related party | Not a related party transaction |
Order size and scope
Diamond Power Infrastructure has received a purchase order from Adani Energy Solutions Limited for 9,059.33 km of AL-59 conductors, made up of 8,948.33 km of AL-59 Lapwing and 111 km of AL-59 Moose. The order is for the ±800 kV HVDC Bhadla–Fatehpur transmission project, a corridor of about 950 km and 6,000 MW linking Bhadla in Rajasthan with Fatehpur in Uttar Pradesh.
The total value is ₹707.80 crore including GST at 18%, against a basic value of ₹599.83 crore before GST, including packing, forwarding, freight and transit insurance.
Pricing follows aluminium and the exchange rate
The purchase order value is based on LME aluminium at USD 2,550 per MT, a premium of USD 106 per MT and USD/INR 87. The order is on commodity back-to-back pricing: each month's supplies are priced under a formula on the average LME aluminium price and USD/INR rate of the month before scheduled dispatch.
The company says this passes movement in aluminium and the exchange rate through, so it does not carry that price or currency risk beyond the pricing period.
How the order compares with the company
At ₹707.80 crore including GST, the order is about 3.2% of the company's market value of ₹21,892 crore at the 19 Nov 2026 close. It is about 67.4% of the consolidated total income of ₹1,050.07 crore it reported for Q2 FY27.
The company says the order marks its entry into the HVDC transmission segment. It also says its integrated rod mills, enhanced conductor capacity and in-house testing facilities leave it well prepared to deliver on schedule.
What the order means for Diamond Power Infrastructure's shareholders
The order adds a contract for HVDC conductors to the company's order book, with a defect liability period of 18 months lot-wise and performance security given by corporate guarantee.
Not stated: the order's share of revenue or order book, the margin on the work, and whether further orders for the HVDC project will follow. The next dated step is the delivery deadline of 31 Dec 2027.
Filed with BSE on . Reference: Original filing (PDF)
Disclaimer:
The information available on this article is provided for education and informational purposes only. It does not constitute or provide financial, investment or trading advice and should not be construed as an endorsement of any specific stock or financial strategy in any form or manner. We do not make any representations or warranties regarding the quality, reliability, or accuracy of the information provided. This website may contain links to third-party content. We are not responsible for the content or accuracy of these external sources and do not endorse or verify the information provided by third parties. We are not liable for any decisions made or actions taken based on the information provided on this website.
Get the Blacklitt app
Hold Diamond Power Infrastructure Ltd.? See it with the rest of your portfolio
Bring in your stocks and mutual funds once. Blacklitt sets them against a plan for your goals and risk, and tells you what to change and why.
Fee-only SEBI Registered Investment Adviser, INA000022428. No commission from any fund house, broker or company.
Scan with your phone camera to get the app.
Investment in securities market are subject to market risks. Read all the related documents carefully before investing.